Gigafactory Texas

Gigafactory Texas

Y CT Cab Bat HQ
Jobs

Summary

Gigafactory Texas

Tesla’s Austin Gigafactory — vehicles, 4680 cells and packs, and HQ/compute on one sprawling campus east of Austin (~2,100 acres).

Background

Chosen in 2020 as Tesla’s central-US vehicle plant as the company moved headquarters to Texas. Empty fields became one of Tesla’s largest hubs: Model Y, Cybertruck, and Cybercab lines, on-site battery work, and a campus that now also hosts energy storage, AI compute (Cortex), cathode production, a Cybertunnel under the highway, crash/test facilities, Optimus robotics, and early chip / advanced-tech site work — still expanding.

Timeline

  1. Start of Construction

    Site work starts on empty fields east of Austin in Travis County.

  2. First Steel and Foundations

    First steel assembly visible and stamping foundations work

  3. Giga Presses arrive

    Huge casting machinery lands for structural vehicle parts.

  4. Cyber Rodeo / official opening

    Opening event and first model Y deliveries from the plant.

  5. Cathode plant site work

    Footers and vertical work begin on the cathode area.

  6. On-site Megapacks (BESS) prep

    First energy-storage pad work shows up on campus.

  7. Megapack BESS installation

    Megapacks land on the campus energy-storage pads.

  8. First Cybertruck built

    First Cybertruck assembled at Giga Texas.

  9. Cybertruck customer deliveries

    Launch event and first customer deliveries from Austin.

  10. Boring / Cybertunnel start

    Tunnel work becomes visible from the air.

  11. AI data center / Cortex build-out

    Supercomputer hall and heavy cable runs take shape.

  12. Cybertunnel structure emerges

    Tunnel structure is clearly visible above and below grade.

  13. Cybertunnel operating

    Trucks move under the highway to staging via the tunnel.

  14. Second Megapack / BESS site rises

    A second Battery energy storage system takes shape.

  15. Test track + Terafab / Optimus site work

    Track asphalt and new factory pads expand the campus.

  16. Test Track construction

    start of construction of the dedicated test track at Gigafactory Texas

  17. Optimus robotics & chip / test-fab site

    Slabs, steel, and chip-area prep for robotics and advanced tech.

  18. Robotics & chip sites grow

    Ongoing construction across the robotics and chip areas.

  19. Cybercab launch

    Launch of cybercab in the robotaxi network in austin.

Job listings

Open roles at Gigafactory Texas

US listings for this plant on Tesla Careers.

Timelapse

Yearly construction stills at Gigafactory Texas

Yearly slideshow from the same satellite stills as Compare — play a year of construction without leaving the page.

Drone flyovers

Aerial clips of Gigafactory Texas

Curated YouTube clips — newest first. Same campus, different altitude.

Independent fan project — not affiliated with Tesla, Inc. Factories move fast; details here can lag